| System voltage and frequency | Nominal network voltage, highest system voltage, and operating frequency. | Select equipment with ratings suitable for the actual network and its insulation requirements; do not choose by nominal voltage alone. | Nameplate ratings, approved drawings, and applicable type-test documentation. |
| Load and fault ratings | Continuous current, short-time withstand current and duration, and peak withstand current. | Ratings should meet or exceed the network study results, including expected load growth and fault-clearing time. | Network fault study, rated-current data, and short-circuit test records. |
| Feeder switching and protection | Whether each feeder needs a load-break switch, switch-fuse combination, or circuit breaker with protection. | Match the switching device and protection scheme to the feeder duty, transformer requirements, and utility protection coordination. | Single-line diagram, protection settings, and device ratings for the intended duty. |
| Internal arc safety | Internal arc classification (IAC), accessible sides, rated arc current, and test duration. | Choose a tested configuration appropriate to the room layout and personnel access. An IAC rating applies only to the tested arrangement and specified conditions. | Type-test report stating IAC classification, accessible sides, current, duration, and installation conditions. |
| Standards and local compliance | Applicable national rules and relevant IEC standards for the equipment and switching devices. | Check the project jurisdiction and utility specifications. Relevant standards may include IEC 62271-1, IEC 62271-200, and the applicable device standard, such as IEC 62271-100, IEC 62271-102, IEC 62271-103, or IEC 62271-105. | Declaration of conformity, standard editions used, test reports, and utility approval where required. |
| Enclosure and installation environment | Indoor or outdoor location, ingress protection, ambient temperature, humidity, altitude, pollution, and corrosion exposure. | Verify the enclosure and derating requirements for the site. IP ratings describe protection against ingress under specified test conditions; they do not replace environmental suitability checks. | IP test data, environmental limits, installation clearances, and any required derating guidance. |
| Insulation medium and environmental impact | Insulation and interruption technology, gas or fluid use, and applicable environmental rules. | Consider lifecycle obligations, leakage monitoring, handling requirements, and current or upcoming restrictions. Confirm that any alternative technology is suitable for the required ratings and site conditions. | Medium specification, environmental documentation, handling procedures, and end-of-life instructions. |
| Operational interlocking | Mechanical and electrical interlocks, earthing-switch operation, key exchange, and indication of switching position. | Confirm that interlocks prevent unsafe operating sequences and align with the site’s switching and access procedures. | Interlock diagrams, operating instructions, and witnessed functional-test results. |
| Reliability and service continuity | Network arrangement, number of ways, cable connections, sectionalizing needs, and availability of spare parts. | Choose a configuration that supports the required switching flexibility and restoration plan; account for planned outages and future expansion. | System operating philosophy, maintenance support plan, and parts availability information. |
| Maintenance and monitoring | Inspection access, condition-monitoring options, required maintenance intervals, and whether components are sealed for life or serviceable. | Base the maintenance plan on the manufacturer’s instructions, operating conditions, and local rules. Do not assume that sealed equipment requires no inspection or operational checks. | Maintenance schedule, inspection checklist, monitoring-system details, and service procedures. |
| Commissioning and future expansion | Cable interfaces, civil dimensions, access space, test points, and provisions for additional feeders. | Check compatibility with cable types and termination systems, room access, lifting requirements, and the planned network layout. | General arrangement drawings, cable-interface details, commissioning tests, and expansion limitations. |